Construction of Kalanki underpass.

Advertisement

The Rs5.27-billion project, which started in June 2013, was scheduled to be completed by 2017. “As the project works have been affected for nearly a year, we expect it will be completed by 2018,” said Pradip Shrestha, spokesperson for the Division Road Office, Lalitpur. “The works have picked up pace since January.” Under the project, the existing two-lane road will be expanded to eight lanes with separate carriageways, service tracks, green belts, bicycle lanes and footpaths on either sides. The 10-km Koteshwor-Kalanki road expansion project has been pushed back by a year due to multiple factors like shortage of construction materials, last year’s earthquakes and subsequent Indian trade embargo that triggered acute fuel shortages.